Spring 2020

Preliminary design and environmental clearances

June 2022

Completed design and plans

Early 2023

Segment 1 construction 

Late 2024

Segment 1 completed

Spring 2025

Segment 2 construction

Traffic Impacts

(All schedules are weather dependent)

INFORMACIÓN ACTUALIZADA DE LA CONSTRUCCIÓN - 23 de octubre de 2024

The South Academy Boulevard Improvements Project is entering its final stages of Segment 1 (north) between Bijou Street and Airport Road, with substantial completion expected this fall. Additional work will take place to finalize various aspects of the improvements. In early October, the section of Airport Road east of South Academy Boulevard will reopen to traffic.  However, drivers should be aware that temporary road alignments and lane closures will remain in place during October. These measures are necessary to ensure the safe completion of the final roadwork.

Expect delays and use alternative routes.