Fall 2024 - Spring 2025

Complete final design and prepare construction documents

Early 2025

Start private utility relocations

Spring 2025 - Fall 2026

Construct storm sewer and surface improvements

Traffic Impacts

  • Construction begins on April 21, 2025.
  • Dublin Boulevard will close to all through traffic from Black Forest Road/Shimmering Creek Drive to Peterson Road for two consecutive nights, April 21 (7 p.m. to 5:30 a.m) and April 22 (8 p.m. to 5:30 a.m.). Follow the signed detour. Local access will be provided between Tutt Boulevard and Black Forest Road/Shimmering Creek Drive.
  • A new traffic pattern on Dublin Boulevard near Peterson Road starts April 21.
  • The Sand Creek Trail will be closed in the area near and underneath Dublin Boulevard from April 21 to early August 2025.
  • Travelers should expect equipment and workers adjacent to the road.
  • The posted work zone speed limit may be reduced to 35 mph.
  • Follow signs and flagger directions when present.
  • View the Construction Updates tab for more information on construction and traffic impacts.