Accessible Routes
BFID: 190361
The walkway contains changes in level greater than a 1/2 inch high that should be ramped.
Changes in level greater than 1/2 inch high shall be constructed as a ramp or curb ramp.
Citation:
2010 ADAS Section 303.4
Changes in level greater than 1/2 inch (13 mm) high shall be ramped, and shall comply with 405 or 406.
As Built:
There is an 8" curb from this direction to access the park.
Recommendation:
Add curb ramp to provide access to these homes and apartments.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190362
The path of contains multiple issues and is not accessible.
The path of travel exceeds the maximum allowable cross and running slope requirements. It also contains changes in level and/or gaps that exceed the allowable maximum requirements. The path of travel does not meet the minimum width requirements for clearances, turning spaces, and/or passing spaces. The floor or ground surface is not firm, stable, and slip resistant.
Citation:
2010 ADAS Section 403.1
Walking surfaces that are a part of an accessible route shall comply with 403.
As Built:
The sidewalk from the corner of Limit and Praderia to the entrance of the park has multiple areas 2-3" vertical displacement, areas with excessive cross slopes to 6.8%, several areas where the path of travel is reduced due to trees, bushes and a guardrail that was installed. The guardrail reduces the path of travel to only 15" wide.
Recommendation:
Replace all sidewalk from this intersection to the curb ramp at the park entrance.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190360
The walkway contains changes in level greater than a 1/2 inch high that should be ramped.
Changes in level greater than 1/2 inch high shall be constructed as a ramp or curb ramp.
Citation:
2010 ADAS Section 303.4
Changes in level greater than 1/2 inch (13 mm) high shall be ramped, and shall comply with 405 or 406.
As Built:
There is an 8" curb from this direction to access the park.
Recommendation:
Add curb ramp and a connecting one to provide access to these homes and apartments.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 187849
There are multiple issues with this curb ramp including:
There is 1/2" lip at the gutter with a gutter slope of up to 15% running at ramp face, the ramp face (red) is up to 9.7% running and 3.4% cross slope, there is no level landing, side flares on both sides has a 12% cross slope and the right flare also has 10.7% running slope from each side of travel.
Citation:
2010 ADAS Section 406
Curb Ramps
As Built:
There are multiple issues with this curb ramp.
Recommendation:
Remove and replace the curb ramp and the landing.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187847
This stretch of sidewalk does not have handrails.
The accessible route of travel exceeds 5% and therefore must be considered a ramp.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
There is 32'' of sidewalk with running slope between 8.2 & 11.3% running slope.
Recommendation:
When this section of sidewalk is replaced, reduce the running slope to 5% if feasible or create ramp with proper slopes, landings and handrails..
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190363
The accessible route contains loose gravel and/or surface materials that do not provide for a stable, firm slip resistant surface.
Citation:
2010 ADAS Section 302.1
Floor and ground surfaces shall be stable, firm, and slip resistant and shall comply with 302.
As Built:
There is currently loose gravel, rock, debris and and orange cone indicating work being done by utilities.
Recommendation:
Clean and patch area.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190365
The accessible route of 31 out of 35 pads has running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails,edge protection, etc.). Cross slopes are greater than 2% across the width of the walk.
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as a ramp. Surface cross slopes must not exceed 1 unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
There are 13 8' pads in this stretch with cross slopes between 2.7-3.4, there are 12 pads with running slopes between 5.8-11.1 and an additional 6 pads with both running and cross slope issues whose high is 3.7 cross slope and 10.2% running slope.
Recommendation:
Fix all cross slope issues and all running slope issues to the maximum extent feasible. Where practical regrade to less than 5%. Other areas may need ramps, with landings and handrails.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190366
The accessible route has running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails,edge protection, etc.). Cross slopes are greater than 2% across the width of the walk.
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as a ramp. Surface cross slopes must not exceed 1 unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
There are 4 8' pads in this stretch with running slopes between 5.3-7.2% running slope and an additional pad with both running and cross slope issues whose high is 2.5 cross slope and 6.5% running slope.
Recommendation:
Fix the cross slope and re-grade to make the route less than 5% running slope.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190367
The concrete expansion joint is spaced greater than 1/2 inch.
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch diameter. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
Citation:
2010 ADAS Section 302.3
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch (13 mm) diameter except as allowed in 407.4.3, 409.4.3, 410.4, 810.5.3 and 810.10. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
As Built:
There is a gap that is 1" wide and 1/2" deep, along with 2 8' pads with cross slopes of 2.8 & 3% cross slope.
Recommendation:
Take out and repour the 2 pads which will fix this joint and both cross slopes.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190368
The concrete expansion joint is spaced greater than 1/2 inch.
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch diameter. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
Citation:
2010 ADAS Section 302.3
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch (13 mm) diameter except as allowed in 407.4.3, 409.4.3, 410.4, 810.5.3 and 810.10. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
As Built:
There is a gap that is 1" wide and 1/2" deep on route to apartment complex.
Recommendation:
Fill the gap.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 187844
There are multiple issues with this curb ramp including:
The bollard in the center of the ramp reduces the clear width to 27" on each side.
The cross slope is up to 16% if someone goes around the bollard.
Citation:
2010 ADAS Section 406
Curb Ramps
As Built:
There are multiple issues with this curb ramp.
Recommendation:
Remove the bollard. If it needs to stay in the curb ramp, off center it so there is at least 36" clear width on one side.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190369
The accessible route has running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails,edge protection, etc.). Cross slopes are greater than 2% across the width of the walk.
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as a ramp. Surface cross slopes must not exceed 1 unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The route to the bench has 3 pads with cross slopes of 2.8-3.8% and 1 of these pads also has a 6.1% running slope. There is also a 3/4" gap.
Recommendation:
Re-grade and pour 3 pads to fix the cross slope and running slope issues which will also take care of the 3/4" gap.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190370
The accessible route has running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails,edge protection, etc.). Cross slopes are greater than 2% across the width of the walk.
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as a ramp. Surface cross slopes must not exceed 1 unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The intersection area has lots of cross slope and running slope problems. The first pad, partially shown about has a 3.5% cross slope, there are another 8 pads with slopes between 2.5 and 5%. These should all be 2% or an easily identifiable route must be at 2% in all directions. There is also a 1.25" gap that is 1/2" deep in this area and other gaps at or over 1/2".
Recommendation:
Fix the pads in the turning space to 2% level in all directions.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190371
The accessible path of travel has cross slopes greater than 2%.
Surface cross slopes shall not exceed one unit vertical in 48 units horizontal (2-percent slope). When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as a ramp.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The route to the picnic table has 5.8% cross slope with a 3/4" wide gap that is 1/2" deep.
Recommendation:
Fix the pads in the turning space to 2% cross slope and fix the gap.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190374
The accessible route has running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails,edge protection, etc.). Cross slopes are greater than 2% across the width of the walk.
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as a ramp. Surface cross slopes must not exceed 1 unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The accessible route around the park has 8 8' pads that have running slopes between 5.9-7.7%, another 10 pads with both running and cross slope problems, the highs for both of this group is 3.7% cross slope and 7.9% running slope. There is also 1 gap of 3/4" and 1 area of 1/2" vertical displacement.
Recommendation:
Fix all cross slope issues to at or under 2% and the running slope on a re-grade to under 5% where feasible and if over 5% we need level landings and handrails.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190373
The concrete expansion joint is spaced greater than 1/2 inch.
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch diameter. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
Citation:
2010 ADAS Section 302.3
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch (13 mm) diameter except as allowed in 407.4.3, 409.4.3, 410.4, 810.5.3 and 810.10. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
As Built:
The route to the picnic table has a 3/4" gap.
Recommendation:
Fill the gap.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190372
The concrete expansion joint is spaced greater than 1/2 inch.
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch diameter. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
Citation:
2010 ADAS Section 302.3
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch (13 mm) diameter except as allowed in 407.4.3, 409.4.3, 410.4, 810.5.3 and 810.10. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
As Built:
The route to the bench has a 3/4" gap.
Recommendation:
Fill the gap.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190375
The accessible path of travel has cross slopes greater than 2%.
Surface cross slopes shall not exceed one unit vertical in 48 units horizontal (2-percent slope). When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as a ramp.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The route to the bench has 3 pads with cross slopes between 2.8-3.7%, along with a 1.34" gap that is 3" deep.
Recommendation:
Fix the cross slopes and fill the gap in the process.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190376
The accessible route has running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails,edge protection, etc.). Cross slopes are greater than 2% across the width of the walk.
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as a ramp. Surface cross slopes must not exceed 1 unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The route around the turn area has multiple issues. There are two running slopes at 6% and 6.5% and a cross slope at 2.6% and 2.8% in two directions with a 3/4" gap and a 1" gap. There is also a turn area with 3 pads with high running and cross slopes between 2.8-4.3% cross slope and 5.5-6.8% running slope.
Recommendation:
Fix this area to 2.% cross slope in all directions and running slope to be under 5%. In te process fill all gaps.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190379
The accessible route has running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails,edge protection, etc.). Cross slopes are greater than 2% across the width of the walk.
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as a ramp. Surface cross slopes must not exceed 1 unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The route to the picnic table has a 3/4" gap and a pad with a 7.5% running slope and an additional pad with a 6.7 running and 2.3 cross slope.
Recommendation:
Re-grade to fix the 2 pads to at or under 5% and 2% cross slope. In the process we will fill the gap.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190378
The concrete expansion joint is spaced greater than 1/2 inch.
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch diameter. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
Citation:
2010 ADAS Section 302.3
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch (13 mm) diameter except as allowed in 407.4.3, 409.4.3, 410.4, 810.5.3 and 810.10. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
As Built:
The route next to the bench has a 1" gap.
Recommendation:
Fill the Gap.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190383
The concrete expansion joint is spaced greater than 1/2 inch.
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch diameter. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
Citation:
2010 ADAS Section 302.3
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch (13 mm) diameter except as allowed in 407.4.3, 409.4.3, 410.4, 810.5.3 and 810.10. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
As Built:
The main accessible route has a 1" gap on the way to the bench.
Recommendation:
Fill the Gap.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190377
The concrete expansion joint is spaced greater than 1/2 inch.
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch diameter. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
Citation:
2010 ADAS Section 302.3
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch (13 mm) diameter except as allowed in 407.4.3, 409.4.3, 410.4, 810.5.3 and 810.10. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
As Built:
The route to the picnic table has a 1" gap.
Recommendation:
Fill the Gap.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190384
The accessible route has running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails,edge protection, etc.). Cross slopes are greater than 2% across the width of the walk.
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as a ramp. Surface cross slopes must not exceed 1 unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The route to the bench has 3 pads with high cross slopes between 2.4-2.6% and 5 separate pads with high running slopes from 5.3% to 7.6%. Also, the bench has the two pads in front of it at 5.3 and 3.5 respectively.
Recommendation:
Re-grade to fix the 3 pads with high cross slopes, including the two in front of the bench to 2% max in any direction. The other 5 pads with high cross slopes must be re-graded and made to at or under 5% running slope or we need level landings with hand rails.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190385
The accessible route has running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails,edge protection, etc.). Cross slopes are greater than 2% across the width of the walk.
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as a ramp. Surface cross slopes must not exceed 1 unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The route to the turn area near the table has 11 pads with running slopes ranging from 5.8-9.5% and 4 pads with both high running and cross slope ranging from 2.7-3% cross slope and 7.7-10.4% running slope. Also in this section is a 1" and a 3/4" gap.
Recommendation:
Re-grade to fix the 15 pads with high cross slopes. It will not be feasible to make these under 5%. The 4 pads with high cross slopes will need to be at or under 2%. Explore adding landings and railing. Make the running slopes to the lowest grade feasible and not over 8.33%. Re-pouring the pads will fix the gaps.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190386
The accessible route has running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails,edge protection, etc.). Cross slopes are greater than 2% across the width of the walk.
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as a ramp. Surface cross slopes must not exceed 1 unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The turn area leading to the picnic table has 3 pads with high running and cross slopes - all in the 4-5% range. Turn areas must be 2% level all directions.
Recommendation:
Re-grade to 2% level in all directions.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190387
The accessible route has running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails,edge protection, etc.). Cross slopes are greater than 2% across the width of the walk.
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as a ramp. Surface cross slopes must not exceed 1 unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The triangle shaped pad has a 5% cross slope, 1/2" gap with 3/4" vertical displacement. The other 2 pads are potentially turn areas with slopes in the 3-5.9% range.
Recommendation:
Re-grade and pour to 2% level in all directions or at least at or under 2% cross slope for the primary direction of travel.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190380
There is no accessible route to the trash enclosure. This area should be at 2% slope on all sides since it is a pivot area.
Citation:
2010 ADAS Section 203.9
Spaces and elements within employee work areas shall only be required to comply with 206.2.8, 207.1, and 215.3 and shall be designed and constructed so that individuals with disabilities can approach, enter, and exit the employee work area. Employee work areas, or portions of employee work areas, other than raised courtroom stations, that are less than 300 square feet (28 m2) and elevated 7 inches (180 mm) or more above the finish floor or ground where the elevation is essential to the function of the space shall not be required to comply with these requirements or to be on an accessible route.
As Built:
The trashcan is on a route that has a 5.8 and 4.9% running slope.
Recommendation:
Move the can and or reduce the slope to 2% in all directions in a turn area for the trash receptacle.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190381
There is no accessible route to the element. IT must be in a level area with 2% slope in all directions since a pivot area.
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements, and accessible spaces that are on the same site.
Citation:
2015 IBC Section 1104.2
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements and accessible spaces that are on the same site.
2010 ADAS Section 206.2.2
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements, and accessible spaces that are on the same site.
As Built:
The dog waste bags and trash receptacle requires a 29" side reach that is 48" high on a 5% slope.
Recommendation:
Move the receptacle to a 2% level area and or create an accessible route to it with no more than a 24" reach.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190382
The concrete expansion joint is spaced greater than 1/2 inch.
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch diameter. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
Citation:
2010 ADAS Section 302.3
Openings in floor or ground surfaces shall not allow passage of a sphere more than 1/2 inch (13 mm) diameter except as allowed in 407.4.3, 409.4.3, 410.4, 810.5.3 and 810.10. Elongated openings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
As Built:
The route to the picnic table has a 3/4" gap leading to it.
Recommendation:
Fill the gap. This may be taken care of in fixing adjacent concrete by trash can.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation