Project Schedule

Sanitary Sewer/Gas Lines

  • Design: Completed Summer 2020
  • Construction: Completed Summer 2021
  • Final Sewer Construction:Completed Summer 2021

Bridge/Culvert, Sidewalks and Waterlines:

  • Design: Completed Fall 2020
  • Completed Summer 2022